How to use the excavation calculator
Digging out a basement, a pool, a foundation trench or a soakaway always produces more spoil than the hole seems to hold. The soil swells as it comes out of the ground, sloped sides add volume at the top of the dig, and the haulage contractor charges by the load. This calculator takes the dimensions of the dig and returns the volume in the ground, the volume in the truck and the number of loads.
- Choose units and a shape. Use a rectangular pit for basements and pools, a trench for footings and service runs (the ends are taken as vertical), or a round pit for soakaways and pier holes.
- Enter the bottom dimensions and the depth. Include working space around foundations in the bottom size.
- Pick the side slope. Choose vertical if the sides will be shored or protected by a trench box; otherwise choose the batter the soil and your local safety rules allow.
- Choose the soil type, which loads a typical swell and shrinkage, or enter your own figures from a site investigation.
- Enter the truck capacity to get the number of loads.
Excavation volume formulas
Top size = bottom size + 2 × slope × depth
Pit volume (prismoidal) = depth ÷ 6 × (Abottom + 4 × Amiddle + Atop)
Trench volume = length × depth × (bottom width + slope × depth)
Round pit volume = π × depth ÷ 3 × (rbottom² + rbottom × rtop + rtop²)
Loose volume = bank volume × (1 + swell) · Loads = ⌈loose volume ÷ truck capacity⌉
Compacted fill = bank volume × (1 − shrinkage)
The prismoidal formula is exact for a pit whose four sides slope at the same angle, which is why it is used instead of simply averaging the top and bottom areas. That shortcut slightly overstates the volume.
| Soil | Swell, bank to loose (estimate) | Bank to compacted (estimate) |
|---|---|---|
| Sand and gravel | 10–15% | About 5–10% smaller |
| Common earth / loam | 20–30% | About 10–15% smaller |
| Clay | 30–40% | About 10–20% smaller |
| Blasted rock | 50–65% | Often 20–30% larger |
These are typical planning ranges from earthmoving references. Real factors depend on moisture, grading and compaction effort; a geotechnical report gives better ones.
Worked examples
A basement dig with 1:1 sides
The bottom is 40 × 30 ft and the dig is 8 ft deep. With 1:1 slopes the top is 56 × 46 ft and the mid-depth section is 48 × 38 ft. Volume = 8 ÷ 6 × (1,200 + 4 × 1,824 + 2,576) = 14,763 ft³, or 547 yd³ in the bank. Common earth at 25% swell makes 683 yd³ loose, which is 69 loads in a 10 yd³ truck. The same spoil would make about 481 yd³ of compacted fill at 12% shrinkage.
A metric foundation trench
A strip footing trench 50 m long, 0.6 m wide and 1.2 m deep with vertical, shored sides holds 50 × 0.6 × 1.2 = 36 m³. In clay at 35% swell that becomes 48.6 m³ loose, or 7 loads in an 8 m³ tipper.
A round soakaway pit
A soakaway 1.5 m across and 1.5 m deep with vertical sides holds π × 0.75² × 1.5 = 2.65 m³. In sandy soil at 12% swell that is 2.97 m³ of loose spoil, which is a single small-truck load or a few skip loads.
Who this calculator helps
- Architects and engineers putting early earthworks quantities on basements, extensions and site works.
- Groundworks and excavation contractors pricing digs, haulage and disposal.
- Quantity surveyors and estimators checking bank, loose and compacted volumes in a bill of quantities.
- Pool, landscape and drainage installers sizing spoil removal for pools, ponds and soakaways.
- Homeowners getting a feel for how many skips or loads a project will produce.
Practical tips
- Price disposal on the loose volume and the weight, not the bank volume; tipping fees are often charged per tonne.
- Work out the concrete for the footings once the dig is sized with the concrete calculator, and the bedding or drainage stone with the gravel calculator.
- Check site falls and batter angles with the slope calculator.
- Keep spoil heaps back from the edge of the excavation; OSHA requires at least 2 ft (0.6 m) in the US.
- Call before you dig to locate buried services, and plan dewatering if the dig goes below the water table.